The Town of Westlake will begin a road sealing project at Solana Boulevard and Granada Trail on May 20th. This project will take 10 to 18 days to complete, weather permitting. Sealing the stained concrete in this intersection will protect the stain from fading over time. The contractor will have two lanes at a time closed throughout the day.
- The first step is to clean the surface which will take 3 to 4 days.
- The next step is to spray the sealer which will take 5 to 6 days then 24 hours to dry.
There is a plan to do other intersections along Davis Boulevard over the next two to three months. We will communicate to everyone the plan before work begins.